Liberty County Community Complex so far has been built in two phases. Phase one was used to demo the old existing school that was on the site. Phase two, which you can see photos of on this page, was used to construct meeting rooms, administrative space, library, swimming pool, and a playground.
All of this work was done using the one-cent Special Purpose Local Option Sales Tax, commonly called SPLOST. In phase two of this project $3.149 million was spent, not one cent of tax payer money was used for this project. Without SPLOST, this would never had been possible.
Phase three of this project is dependent on another SPLOST, it would include renovating the gym, adding a walking trail, and placing a band stand in the green space. However, without SPLOST, this project will not happen.